Digger on the Montgomery Canal for the reinstatement of Schoolhouse Bridge

After four years of preparation, work on the Montgomery Canal restoration took another step forward as the programme to rebuild Schoolhouse Bridge, south of Crickheath, near Oswestry, got under way.

The initial phase of this project involves enclosing land at the bridge site generously provided by adjoining farmers. A trackway will be laid to allow larger vehicles to by-pass the site when the lane is closed with a diversionary route provided for this popular section of the towpath.

Continue reading “More progress on Montgomery Canal restoration”

Canal Clearance work started south of Crickheath

Volunteers on the towpath of the Montgomery Canal

The Shropshire Union Canal Society started work at the beginning of August on clearing the vegetation on the next dry section of the Montgomery Canal at Crickheath in Shropshire.

This clearance marks a milestone in the recent restoration work as it sees work on a section south of the current restoration efforts and it will facilitate the inspection of the canal bed and walls at Crickheath Wharf to assess remedial work needed.

Continue reading “Canal Clearance work started south of Crickheath”