More progress on Montgomery Canal restoration

Digger on the Montgomery Canal for the reinstatement of Schoolhouse Bridge

After four years of preparation, work on the Montgomery Canal restoration took another step forward as the programme to rebuild Schoolhouse Bridge, south of Crickheath, near Oswestry, got under way.

The initial phase of this project involves enclosing land at the bridge site generously provided by adjoining farmers. A trackway will be laid to allow larger vehicles to by-pass the site when the lane is closed with a diversionary route provided for this popular section of the towpath.

Continue reading “More progress on Montgomery Canal restoration”

Canal Clearance work started south of Crickheath

Volunteers on the towpath of the Montgomery Canal

The Shropshire Union Canal Society started work at the beginning of August on clearing the vegetation on the next dry section of the Montgomery Canal at Crickheath in Shropshire.

This clearance marks a milestone in the recent restoration work as it sees work on a section south of the current restoration efforts and it will facilitate the inspection of the canal bed and walls at Crickheath Wharf to assess remedial work needed.

Continue reading “Canal Clearance work started south of Crickheath”

Volunteers return after the Lockdown

Before the lockdown, the Shropshire Union Canal Society had been making good progress restoring the canal between Lloyds Animal Feeds compound and Crickheath despite the heavy rain at the beginning of March.

During their absence however, the canal had quickly become overgrown and so volunteers had to start by clearing weeds and a fallen tree on the first working party which took place on 24th – 26th July.

Continue reading “Volunteers return after the Lockdown”

Restoration on the Monty due to resume

The Shropshire Union Canal Society has announced that restoration work on the Montgomery Canal is to resume following the enforced cessation due to Covid 19.

The lockdown followed an incredibly wet winter and seriously affected plans to complete the remaining dry section of the channel, to link the national network with the newly constructed winding hole terminus at Crickheath in 2021. Now, however, planning is taking place to resume activities in August, albeit, with a much more regimented and selective approach than before.

Continue reading “Restoration on the Monty due to resume”
The Montgomery Canal - Camlas Maldwyn
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.